Welcome to the fourth edition of our newsletter. With the site progressing well and sales now underway we would like to take this opportunity to update you on what’s been going on over the last few weeks.

Summary of Progress to Date

  • CAPTAIN’S VIEW
    The site is progressing well, and our first 14 homes have been handed over to our new residents. Several other plots are also nearing completion. Landscaping on Braunton Crescent is complete with flowers well in bloom.
    Since our show home has opened we have sold all 30 houses currently available with Block B flats now on sale. Apartments are expected to sell well on the back of the sales of the houses.
    As a result of sales success to date the show home is currently closed on Tuesdays and Wednesdays.
  • CAPTAIN’S WALK
    The first plots are now fully plastered with other internal works ongoing. The superstructures of plots 91 to 106 are now complete with plots 85 to 94 at various stages of brickwork.
    Foundations and substructures for the block of flats on this site are now complete with external superstructure at first lift brickwork. All substructures for the whole development on both sites are now complete.

Community Engagement/initiatives

  • We are looking to engage with local schools to carry out a Considerate Constructors Scheme competition.
  • Please get in touch if you would like to get involved or if you have any community projects you would like to tell us about at communities@cardiffliving.wales

You Said We Did

Due to the recent dry weather conditions dust has become an ongoing issue on the roads surrounding the site. To address this issue we’ve brought a large bowser on to site to water the ground and help suppress dust levels. We apologise for any inconvenience or issues this may have caused and would like to assure you that we are constantly looking at ways to improve and reduce impact that the site works have on local residents.

Future Works

We will continue to progress build on site as we seek to complete more homes. The first 6 Council homes at Captain’s Walk will be available from the end of October.

Site Contact Details

Project Manager – Stephen James: 07825 342736
Site Manager – Jamie Monk: 07917 155173
Site Manager – Steve Sinclair: 07715 619622
Assistant Site Manager – Lisa Bailey: 07887 6505580

Our Permitted Site Working Hours are

Monday to Friday 8am to 5.30pm